FAQ
Questions from the neighborhood.
Plain answers about PAX-1 to the questions we hear most, each with the record behind it and the page that has the rest.
The project
- What is PAX-1, and where is it?
PAX-1 is a planned hyperscale data center campus in Middlesex Township, Cumberland County: 16 warehouse-sized buildings full of computer servers that run day and night. You'll also see it called Pennsylvania Digital 1 or Project Bolt.
It covers about 694 acres of farmland at 246, 248, 250 and 256 Country Club Road. That's north of Country Club Road and Interstate 81 and west of Bernheisel Bridge Road, with the Conodoguinet Creek along its northern and western edges. It sits just east of Carlisle, a third of a mile from the Appalachian Trail.
View the project overviewView the four parcelsView the Park Service letter
- Who is building it, and who will use it?
The owner and applicant is Carlisle Development Partners, LLC, of McLean, Virginia, a joint venture of Pennsylvania Data Center Partners and PowerHouse Data Centers. In July 2025 it bought the four farm parcels for $44 million.
The company that will use the buildings hasn't been named. In February 2026, the developer's engineers wrote that “the end user, who has recently joined the project,” would use on-site water storage, without naming it. On June 26, 2026, Supervisor Phil Neiderer told residents, “The tenant has not yet been named.”
A side agreement approved September 2, 2026, which the Phase 1B approval requires the developer to follow, says only that the developer “may need to identify” the tenant for the first six buildings before the Township approves any later final plan.
View the emailsView the $30 million deedView the $14 million deedView the engineer's answerThe tenant clauseWatch him on the tenant
- How big is it?
- 694 acres, almost six Hersheyparks.
- 16 data center buildings on three campuses: six on Campus 1 and five each on Campuses 2 and 3.
- Two stories each, with 100,000 to 200,000 square feet per floor. Most are about 900 feet long and 200 feet wide.
- About 4.2 million square feet in all, in the developer's 2025 traffic study, which assumed 18 buildings. Supervisor Phil Neiderer put it at around 5 million at full buildout.
- Up to about 83 feet tall at the rooftop penthouses on the developer's own drawings, with walls about 72 feet tall. The zoning under and around the site limits buildings to 40 feet.
- Three new electrical substations, plus a PPL switchyard.
- The developer calls it a $15 billion project.
View the project overviewView the traffic study's figuresView the April 1 minutesRead it in the hearing transcriptWatch the heightsWatch the dimensions
- How many homes are near it?
260 homes stand within 1,000 feet of the site, the nearest about 80 feet from the property line, and 1,333 within a mile, on both sides of the Conodoguinet Creek.
- Will it affect the Appalachian Trail?
Pennsylvania's State Historic Preservation Office says yes. The Trail passes a third of a mile from the site. On January 23, 2026, the office disagreed with a visual analysis that had found no adverse effect, and concluded that construction “will have an Adverse Effect on the Appalachian Trail viewshed by obscuring views of open space that contribute to the significance of the resource.” In March it said planting 100 evergreens along the Trail would not be “an appropriate minimization measure.” Its letter of May 26, 2026 still treated the adverse effect on the Trail as unresolved.
The Appalachian Trail Conservancy says the buildings would be visible along about 800 feet of the Trail, a seven-minute walk. At the May 6, 2026 Township meeting, its representative said, “we are in opposition of the location, size, and scale of this data center.” On September 2, the Conservancy asked the Supervisors to deny the Phase 1B final plan and every plan after it.
View the determinationView the follow-up letterView the May 26 letterView the Conservancy's letterWatch the Conservancy on May 6Watch it on September 2
- When will it be built? Is work already happening?
Yes, work is under way. In March 2026, Supervisor Phil Neiderer said the work then under way was mainly relocating a water main along Country Club Road. Blasting began April 1, 2026. The Township gave Phase 1A final approval on May 6, and state stormwater coverage for Phases 1A and 1B followed on May 18. On June 15, one blast went over the state's limit for air blast, 140.5 decibels against 133, and DEP cited the blasting contractor.
The developer's schedule runs through spring 2032:
- Phase 1A, the roads and the grading for the substations and the PPL switchyard: March to November 2026.
- Phase 1B, Campus 1's six buildings, a new building shell started about every three months: June 2026 to December 2028.
- Phase 2, Campus 2: March 2028 to May 2030.
- Phase 3, Campus 3: August 2029 to spring 2032.
View the March 27 minutesView when blasting beganView the Phase 1A approvalView the stormwater approvalView the DEP reportView the scheduleView the later phases
Your home
- How much electricity will it use? Will my electric bill go up?
In an October 30, 2025 letter, PPL said it can supply about 1.35 gigawatts of peak demand to the site, and that “certain system upgrades will be required.” PPL says the cost of those upgrades “will be allocated in accordance with the Company's tariff,” and that connecting large customers like data centers “helps lower the transmission component of energy bills for all customers.”
Our grid's independent monitor found data centers added $29.4 billion to the region's capacity costs for June 2025 through May 2029. PPL says higher capacity prices have added about $20 a month to its average home's bill.
No independent analysis of what PAX-1 means for Middlesex ratepayers has been made public. The Township's zoning ordinance asks a data center applicant for its interconnection agreement with the utility, and for any known impacts on electric rates. When the Township's engineer asked for both, the developer replied that PPL “will not publicly release the interconnection agreement.” It also said the ratepayer study it had submitted would be removed from its environmental assessment and “treated as reference material only.”
View PPL's letterRead the grid monitor's reportSee PPL's pageView the ruleView the response
- How much water will it use, and where does it come from?
It can draw up to 400,000 gallons a day from the public water system. On January 15, 2026, the Middlesex Township Municipal Authority approved that allocation, plus 273,000 gallons a day of sewer capacity. The authority's water comes from wells.
That's more than 40 percent of the system's spare capacity. In September 2025, the developer's own consultant put the system's available capacity at about 910,000 gallons a day, rising to about 1.35 million once a new municipal well comes online. Supervisor Phil Neiderer has told residents the authority will have a “kill switch” to shut off water to the data center if it goes over its allocation.
On the hottest days, the campus would need far more. That same consultant put peak demand at full buildout at roughly 3 to 4 million gallons a day, a figure not yet finalized. A November 2025 memo from the developer's water engineers estimated peak-day cooling needs of 850,000 gallons for the first phase and up to 2.55 million at full buildout. The plan is to fill large storage tanks on the site from the public supply over time, and draw them down in summer.
In January 2026, the Township's engineer wrote that the project “is taking all available additional capacity not currently identified by ‘Future Development Allocations.’” The engineer also wrote that the authority's new Well 2 should be finished, noted as June 2027, “before this project should be connected to the public potable water systems.” Those comments were advisory. The engineer noted that the authority “ultimately has jurisdiction over water and sewer service.”
In September 2026, the developer agreed not to ask for more than 400,000 gallons a day, based on the authority's current capacity.
View the allocationView the capacity figuresView the March 27 minutesView the consultant's reportView the cooling water tableView the engineer's reviewView the water cap
- Will it affect my well?
The data center is to run on public water, not wells on the site. The Township's approvals bar new wells on the property and require existing ones to be sealed. But public water here is groundwater too: the authority pumps it from wells.
The Township's own ordinance says “No data center shall be approved without sufficient water and/or for a use that poses adverse impact on existing wells in the vicinity.” It requires a water feasibility study that maps the wells within 1,000 feet and looks at the effects on nearby wells, streams and groundwater. When the Township's engineer asked for that study, the developer answered that its water and sewer agreement with the authority “was executed on 01/15/2026.” Our appeals argue that the study, and the river basin commission's approval the ordinance also requires, are still missing.
About 16 of the homes within 1,000 feet of the site likely rely on private wells, and Pennsylvania's rules for construction blasting require no survey of nearby wells. The side agreement approved September 2, 2026 calls for the developer to test the wells of willing owners within 1,500 feet of blasting, and to fix or replace any well that blasting harms. If your well is in that zone, ask the Township or the developer about signing up.
View the no-wells conditionView the ruleView the developer's answerRead our appeal on itRead the state's blasting rulesView the side letter
- How many diesel generators will there be? What about the air?
At least 582. The developer's April 2026 noise study counts 566 emergency generators rated 2.5 megawatts each, plus 16 smaller house generators. That's more than 1,400 megawatts of diesel generating capacity.
Cumberland County's air already gets an F from the American Lung Association for short-term particle pollution. The developer's engineer told the Supervisors that because of the number, testing the generators is “a daily activity that will occur.” How often they'll actually run, and what they'll emit, hasn't been settled. In June 2026, Supervisor Phil Neiderer said the tenant will determine the number of generators, and that DEP's air quality permit, issued at final land development, will set when they can run.
As of September 23, 2026, the developer hadn't applied for the campus's air quality permits. The side agreement requires it to give the Township copies of its air permit filings. We'll post them when they're public.
View the equipment tableSee the county's gradesSee the trackerThe air termsWatch “a daily activity”Watch him on the tenant
- How loud will it be?
Middlesex's rule for data centers sets one number: noise “shall not exceed 70 dBA, as measured at the property line.” That limit “does not apply during a time of power outage,” which is when the developer's study runs every generator on the site at once. The rule sets no separate limit for low-frequency sound.
How loud is 70? The developer's own noise study says a 60 dBA setting, like a large business office, is one where “sleep might be difficult.” It also says a 10-decibel increase sounds about “twice as loud.” To protect sleep, the World Health Organization advises no more than 45 decibels outside homes at night.
That study predicts about 50 dBA at the nearest property line in normal operation, and about 51 during generator maintenance. Those are computer-model predictions, prepared for the developer's engineers. The side agreement calls for 24 months of noise monitoring at the property line after construction, with the results posted online every month.
View the noise limitView the noise studyView the study's scaleRead the 1999 WHO guidelinesThe noise terms
- What will it do to traffic on Country Club Road?
The developer's June 2025 traffic study projects about 2,900 vehicle trips a day at full buildout. It recommended no improvements at the three nearby intersections it studied, including Harrisburg Pike and Country Club Road. Its recommendations covered only the site's own driveways.
The developer's agreement with the Township, approved September 2, 2026, goes further. It requires:
- a right turn lane on Harrisburg Pike;
- monthly reports on the condition of Country Club Road during construction, with a repair plan for any stretch whose pavement score drops below 50;
- a full rebuild of Country Club Road once construction is complete.
The plans also call for widening Country Club Road along the site. Before Phase 3 can get final approval, the developer must submit a detailed plan for Country Club Road.
View the traffic studyView the recommendationsView the developer's agreementView the road reportsView the full rebuildView the road wideningHear the road condition
- Will it hurt my property value?
We don't know of any study of property values around this site. The only study we've found in Township records is a George Mason University note on Northern Virginia, which the developer's lobbyist sent to Township, county and state officials in September 2025. It found no statistical evidence that being near a data center lowered home values there in 2023. We haven't seen an independent study of this site, and we won't guess at a number.
Jobs, taxes and agreements
- What about the jobs and tax money?
These are projections, and the developer's own numbers don't line up.
- At the May 30, 2025 hearing, the developer's attorney told the Supervisors its real estate taxes would run “in the tens of millions of dollars annually.”
- The developer's environmental assessment listed 250 staff at full buildout in one section and 225 permanent positions in another. On a single page, it put the Township's property tax revenue at $10.1 million and its “Net Township Impact” at $8.8 million. In October 2025, the Township's engineer flagged both, noting the two dollar figures “seem to reference the same topic, but are different values.”
- When PowerHouse first presented the project in October 2024, the minutes describe a two-story, 300,000-square-foot data center building with “approximately fifteen employees.”
We haven't found job counts or tax revenue projections in any of the Township's approval conditions, or in the agreements approved September 2, 2026.
Read it in the hearing transcriptView the reviewView the minutes
- What is the $14 million community benefits agreement?
On September 2, 2026, the Supervisors approved an agreement in which the developer will pay the Township $14 million for land preservation, public safety, parks and property tax relief. It's paid in six installments of $2,333,334. Each is due within 30 days of a milestone: construction starting on each of the three campuses, and occupancy of Building 1 on each campus.
While legal challenges are pending, each payment goes into an escrow fund held by the developer's counsel. It's released to the Township only when the challenges are “fully and finally resolved.”
View the agreementView the paymentsView the escrow termsWatch the vote
- What else did the Township get in writing?
A side agreement, approved September 2, 2026, lists terms the Township may attach to future final approvals. The Phase 1B final approval includes a condition that the developer comply with it. Under the agreement, the developer is to:
- test the wells of willing owners within 1,500 feet of blasting, and fix or replace any well that blasting harms;
- monitor noise at the property line for 24 months after construction, and post the results online every month;
- give the Township copies of its air permit filings;
- remove waste and hazardous materials if the data center use ever stops, backed by $5 million in security, due within 30 days after it gives notice it is stopping, or after the use has stopped for 12 months in a row;
- test its industrial wastewater every month for 24 months.
Note the limits. The $5 million covers disposal of waste and hazardous materials. It doesn't cover taking down 16 buildings. And the well testing covers blasting damage, not long-term water use.
View the side letterThe noise termsThe air termsThe $5 millionThe wastewater termsHear the condition
How we got here
- How was a data center allowed on land planned for homes?
Through a zoning overlay. Think of it as a sticker placed on top of the zoning map that adds a new use for the land underneath.
On May 30, 2025, the Supervisors adopted Ordinance 3-2025. It put a Data Center Overlay on four parcels covering 694 acres on Country Club Road, and made data centers a use “permitted by right” there. On September 3, 2025, the Township adopted its new zoning ordinance, Ordinance 7-2025, with the overlay built in.
Before the overlay, the land had been planned for housing. Part of it was covered by a state stormwater permit first authorized in December 2018 for a 58-unit housing development. That same permit has since been amended to cover the data center.
The four parcelsView the by-right usesView the ordinanceRead the permit's start
- Who wrote the overlay ordinance?
Read the emails and decide for yourself.
On December 4, 2024, nearly six months before the public hearing, the developer's attorney emailed the Township's zoning officer and copied its planning consultant: “Attached is a draft of a data center overlay for the Township's draft new Zoning Ordinance.” He included a map of the overlay's boundary. On January 7, 2025, the consultant wrote back to him: “we're getting close and we have the Data Center Overlay language incorporated into the draft.” These were private emails. Residents got copies later through Right-to-Know requests.
Today about 80 percent of the overlay in the zoning law matches the attorney's draft, word for word.
At the May 30, 2025 hearing, the attorney told the Supervisors, “it's not like this amendment was, you know, we submitted something and, you know, it's what you are adopting.” He said the Township's planning consultant, working with the county planning department, developed the standards.
View the attorney's emailView the consultant's replyThe overlay todayRead it in the hearing transcript
- How fast did it move, and who raised concerns?
- April 17, 2025: The County Planning Commission voted unanimously to deny approval of the Township's whole draft zoning rewrite “until CCPC comments are addressed.” The developer's overlay had already been folded into that draft.
- April 25, 2025: The developer's attorney asked the Supervisors to adopt the overlay on its own, as an amendment to the Township's 1989 zoning ordinance. He called it a backup plan, saying PPL was allocating power “on a first-come, first available basis.” The Supervisors set a hearing for May 30 at 7:30 a.m. The developer offered to pay “any and all advertising costs.”
- May 15, 2025: County planners recommended approving the standalone overlay, with comments. They recommended putting it in the new ordinance instead, while noting that “a major data center project warrants an expedited update.” They suggested buffers to protect sensitive features such as the views from the Appalachian Trail, and said the Township should consider adopting a new comprehensive plan to replace its plan from 2003.
- May 30, 2025, 7:30 a.m.: Five people spoke during public comment. Each raised concerns or asked the Supervisors to wait for more information on water, power and noise. One asked whether the water authority had been told how much water the data center would use. The Township solicitor said he had no idea. So did the Board's chairman, who also sits on the water authority, adding that it was drilling another well. The developer's attorney said those details would come later, at the land development stage. The Supervisors adopted the overlay unanimously that morning, 35 days after they first took up the request.
View the county's voteView the April 25 minutesView the county's reviewView the county's commentsView the hearing transcriptThe chairman's answerThe attorney's answer
- Could more data centers come to Middlesex?
The Supervisors have voted not to consider new data center zoning for now. In February 2026, they voted to allow no zoning changes or new overlays “permitting or expanding data center use” until the Township adopts an updated comprehensive plan. The current plan dates to 2003. A request to stretch the overlay over about 214 more acres along Harrisburg Pike is on hold under that vote, and county planners recommended against it.
There are three caveats. The vote is a Board decision, not an ordinance. It doesn't touch the existing overlay. And the 2025 zoning law also permits data centers by right in the Township's industrial district.
View the minutesView the county reviewView the data center row
- What has the Township approved so far?
Date Approval September 26, 2025 The laydown yard for PPL's substation work, with nine waivers January 5, 2026 Preliminary subdivision into five lots March 4, 2026 Phase 1A preliminary plan May 6, 2026 Final subdivision, Phase 1A final plan and Phase 1B preliminary plan, with 29 waivers, modifications and deferrals across the three July 1, 2026 Phase 1C and Phase 2 preliminary plans September 2, 2026 Phase 1B final plan, for Campus 1's six buildings, conditioned on the side agreement. Phase 3 preliminary plan. The sewage planning module. The master developer's agreement and its Phase 1B amendment. The $14 million community benefits agreement. Final plans for Phases 1C, 2 and 3 still have to come before the Supervisors.
View the laydown yard approvalView the January 5 minutesView the March 4 minutesView the subdivision approvalView the Phase 1A approvalView the Phase 1B approvalView the Phase 1C and 2 appealWatch the Phase 1B final motionWatch the vote
- Why didn't the Supervisors just vote no?
Before voting on September 2, 2026, Supervisor Phil Neiderer pointed to this website to make the point: if a use is permitted by right and meets the zoning ordinance, the Supervisors must approve it.
That's why the 2025 overlay vote mattered so much. In Middlesex, a warehouse, a truck terminal and a solid waste facility each need a public hearing, where the Supervisors can set conditions or say no. A data center doesn't. Once data centers were permitted by right on these 694 acres, the fight turned to two questions. Is the overlay itself lawful? And do the plans meet every requirement?
The Supervisors still made choices along the way. They voted on every waiver, modification and deferral the developer asked for, in motions separate from the plan approvals, including 29 on May 6 and 18 more on September 2.
View the uses that need a hearingWatch him say itWatch the Phase 1B reliefWatch the Phase 3 relief
The agencies
- Have regulators found problems?
Yes. Several are on the record:
- The State Historic Preservation Office found an adverse effect on the views from the Appalachian Trail. It was still unresolved as of May 26, 2026.
- The Cumberland County Conservation District found 82 technical deficiencies in the stormwater application on March 30, 2026. On May 1, 21 were still open, and 3 new ones had been found. Coverage was issued May 18.
- The same district's inspection on August 5, 2026 cited two violations: erosion controls not maintained, and idle ground not stabilized. Its report says the violations it notes “constitute unlawful conduct” under the Clean Streams Law.
- DEP cited the blasting contractor after a blast on June 15, 2026 went over the state's limit for air blast.
- In August 2025, DEP issued a notice of violation for a line laid without a permit through a wetland channel on one of the parcels. It went to Club Road Properties, the developer of the earlier Cumberland Knoll housing project, and its excavator. The line was a sewer line for Cumberland Knoll, laid across a parcel DEP says Club Road didn't own. The data center developer bought that parcel in July 2025, and its engineer agreed to apply for the permit after the fact.
View the determinationView the May 26 letterRead the 82 deficienciesRead the May 1 countView the inspection reportView the DEP reportView the notice of violation
- What's the problem with the stormwater permit?
PAX-1's construction stormwater coverage didn't come from a new permit. It came from amending an old one.
That permit, PAC210079, was first authorized in December 2018 for a 58-unit housing development on 15.3 acres. After four amendments, it now covers the 693-acre site, with 300 acres of earth disturbance. On March 30, 2026, the conservation district found 82 technical deficiencies in the application for the fourth amendment. On May 1, 21 were still open and 3 more had been found. Coverage was issued May 18.
On June 16, 2026, two families asked DEP for an informal hearing. DEP issued its determination on July 16. On August 13, the families appealed to the Environmental Hearing Board, Docket No. 2026-095-CS. The appeal argues that a project this size should have needed an individual permit, with full public notice. It asks the Board to vacate DEP's determination and revoke the coverage.
Read the permit's startView the fourth amendmentRead the 300 acresRead the May 1 countView the hearing requestView DEP's determinationRead what the appeal asks
- What does the Susquehanna River Basin Commission have to do with it?
The Susquehanna River Basin Commission oversees large water use in our watershed. The Township's ordinance requires a data center's water feasibility study, filed with its zoning permit application, to include “proof of review and approval” from the commission if the project will consume 20,000 gallons a day or more over a 30-day average.
On May 28, 2026, a commission official told us his answers were “based on the limited verbal information we have received.” On that basis, he said:
- PAX-1 is expected to consume at least 20,000 gallons a day for part of the year;
- the operator must get the commission's approval before operating;
- that requirement had been “fully communicated” to the developer;
- the commission had not received an application.
The municipal authority has also asked the commission to approve its new Well 2, for up to 914,000 gallons a day. The commission tabled that request at its June 4 and September 16, 2026 meetings.
View the ruleView the emailRead the June noticeRead the September notice
The legal challenges
- What legal challenges are pending?
There are five, all filed by local residents.
- The spot zoning challenge, filed with the Zoning Hearing Board on May 13, 2026. The board never advertised or held a hearing, and the residents argue that after 60 days, that counts as a denial under state law. On August 6, 2026, they took the challenge to the Cumberland County Court of Common Pleas, No. 2026-08758. They're asking the court to hold hearings and declare the overlay invalid.
- The appeal of the May 6 approvals, filed June 5, 2026, No. 2026-06465.
- The appeal of the July 1 approvals of Phase 1C and Phase 2, filed July 31, 2026, No. 2026-08652.
- The appeal of the September 2 approvals of the Phase 1B final plan and the Phase 3 preliminary plan, filed October 2, 2026, No. 2026-11177.
- The stormwater permit appeal, filed with the Environmental Hearing Board on August 13, 2026, No. 2026-095-CS.
View the challengeView the county court appealView the May 6 appealView the Phase 1C and 2 appealView the September 2 appealView the stormwater appeal
- What is spot zoning, and why do you think it applies here?
In plain English, spot zoning is when a township singles out a parcel for the benefit of one user and treats it differently from the land around it. Our challenge relies on Pennsylvania court decisions going back to 1965. It argues that's what happened here:
- The overlay covers only the developer's four parcels.
- When it was adopted in May 2025, data centers were permitted by right there “and nowhere else in the Township.”
- Its text started as a draft from the developer's attorney.
- It went from request to adoption in 35 days, under a 2003 comprehensive plan that county planners said the Township should consider replacing.
- A hyperscale campus is incompatible with the farms and homes around it.
The challenge also argues that the overlay violates the Environmental Rights Amendment of the Pennsylvania Constitution, Article I, Section 27. We're asking the court to strike it down.
View the case lawView the challengeView the county court appealView the county's commentsRead what the challenge asks
- Has a court ruled on anything yet?
Yes, in two of the cases. On September 22, 2026, the Court of Common Pleas ruled on the developer's motion to quash, or dismiss, our appeal of the May 6 approvals:
- It dismissed the parts challenging the final subdivision and the Phase 1A final plan.
- It kept alive the challenge to the Phase 1B preliminary plan, which covers Campus 1's six buildings. Our brief is due by November 2, and the Township and the developer have 30 days after that to respond. Oral argument is set for January 12, 2027, at 10:30 a.m., in Courtroom No. 4 of the Cumberland County Courthouse.
- It denied our request to pause the approvals while the appeal goes on, “without prejudice to refile.” That means we can ask again.
On September 30, in the spot zoning case, we asked the court to halt construction and further approvals until that case is decided. On October 5 the court ruled on part of that request:
- It found that the mandatory hold in state law doesn't apply, because it covers only hearings pending before the Zoning Hearing Board.
- On our request for a new hold, it scheduled an evidentiary hearing on the merits of the case for November 13, 2026, at 2 p.m., in Courtroom No. 1 of the Cumberland County Courthouse.
The other cases are at earlier stages. In the stormwater appeal, the Environmental Hearing Board has set discovery to close on February 10, 2027.
View the rulingView the court's scheduleView the stay rulingView our request to enforce the holdView the October 5 orderView the order setting the hearingView the Board's schedule
- Bulldozers are already moving. Isn't it too late?
Yes, bulldozers are rolling. That doesn't settle the legal questions.
- Our land use appeals ask the court to reverse plan approvals, and the spot zoning challenge asks it to throw out the overlay itself.
- Only Phases 1A and 1B have final approval. Phases 1C, 2 and 3 still need it.
- The river basin commission says the operator needs its approval for consumptive use before it can operate.
- The state's finding of an adverse effect on the Appalachian Trail was still unresolved as of May 26, 2026.
- Even the developer's $14 million agreement acknowledges “several legal challenges pending,” and holds its payments in escrow until they're resolved.
The developer has chosen to keep building while the appeals are pending.
Read what the challenge asksView the emailView the May 26 letterView the escrow terms
About us
- Who is Stop PAX-1, and where do your documents come from?
We're neighbors: families who live around the site and across Middlesex. We started reading the documents and didn't like what we found. We're not activists or experts, just ordinary people. Our legal challenges are filed by local residents and handled by Pennsylvania attorneys.
Almost everything we cite is public record: township minutes, ordinances, plans, agency letters and permits. We got most of it through Pennsylvania's Right-to-Know Law. We put each document beside what we say, and keep the key ones on our Documents page, so you can check our work. The figures we worked out ourselves are on Check Our Math, with each input and the arithmetic. If we got something wrong, tell us. We'll fix it and list the correction.
- How can I help, and where does the money go?
- Give to the legal fund. 100% goes to the legal fund: briefs, expert witnesses and transcripts. Donations go through GiveSendGo to Neighbors Against PAX-1.
- Show up. The Supervisors usually hold regular meetings on the first Wednesday of the month at 6:00 p.m., and workshops on the last Friday at 7:30 a.m. Meetings move, so check the calendar.
- Put out a yard sign. Request one, and we'll bring it to you.
- Sign the petition, volunteer, and send this page to one neighbor.
Signatures get attention. Lawyers stop bulldozers.
- Can I speak at a Township meeting?
Public comment is for residents and taxpayers of Middlesex Township, three minutes each. Anyone else can send a written comment. Meetings move, so check the calendar before you go.
Fund the fight
Lawyers stop bulldozers.
The answers above are why we're in court. The cases run on briefs, expert witnesses, and filing fees.