Timeline

Updated July 19, 2026

See how we got here.

This was pushed through with real gaps. Here they are, in chronological order. Every date is on the public record, and most link directly to the source document.

17 milestones · 137 in the full record

2024

October 25, 2024Developer

At a Board workshop, the developer's attorney, PowerHouse CEO Doug Fleit, and the project team present the data center concept for the first time; the supervisors voice support the same day and send it to the Planning Commission. The minutes record no public comment.

December 4, 2024Developer

The developer's attorney emails Zoning Officer Mark Carpenter and the township zoning consultant a pre-drafted Data Center Overlay ordinance for the township's new zoning ordinance — sent outside any public meeting.

2025

January 7, 2025Township

The township zoning consultant confirms to the developer's attorney: "we have the Data Center Overlay language incorporated into the draft." The developer's text is now in the township's ordinance.

April 25, 2025Township

At a workshop, the developer's attorney urges speed — PPL power will be allocated on a "first-come, first available basis" — and the Board schedules the overlay hearing for May 30, with the developer paying for the advertising. The 35-day clock starts.

May 30, 2025Township

At a 7:30 a.m. hearing with — in a supervisor's own later words — "very little public attendance," the Board unanimously adopts Ordinance 3-2025, the Data Center Overlay. Thirty-five days after the Board took up the request.

July 15, 2025Federal

PAX-1 is announced as a ~$15 billion project at Senator McCormick's Energy and Innovation Summit; developer Igal Feibush joins a private roundtable with the President.

August 7, 2025State

DEP issues a Notice of Violation for the unpermitted line through the wetland on Country Club Road, citing the Clean Streams Law, and requests an after-the-fact permit application.

August 12, 2025Residents

Residents pack a township meeting with questions about the data center; PennLive reports the first organized resistance and skepticism.

September 3, 2025Township

The Board adopts Ordinance 7-2025, the comprehensive zoning rewrite: the overlay is folded in as Section 2.18, the land under it becomes MU-1 "Mixed-Use Neighborhood," and data centers become by-right in the Industrial district.

2026

January 5, 2026Township

The Board conditionally approves the preliminary subdivision: 693 acres, five lots, one data-center development.

January 23, 2026State

The State Historic Preservation Office rejects the developer's "no adverse effect" memo and formally finds the project WILL have an adverse effect on the Appalachian Trail.

April 13, 2026Developer

The developer's own noise study is completed: 532 generators across the campus.

May 6, 2026Township

In one meeting, the Board conditionally approves the final subdivision, the final Phase 1A plan, and the preliminary Phase 1B plan — 29 more waivers, modifications, and deferrals of township standards across the three approvals.

May 13, 2026Residents

Five couples who live beside the site file a substantive validity challenge with the Zoning Hearing Board, arguing the Data Center Overlay is illegal spot zoning. Pennsylvania courts have been striking down spot zoning where they find it since the 1960s; the challenge asks the Zoning Hearing Board to find it here.

June 3, 2026Residents

The residents appeal the May 6 approvals to the Cumberland County Court of Common Pleas, asking the court to review whether the township followed its own ordinances.

June 29, 2026Township

Nine days before the hearing, the residents' attorney Nathan Wolf calls the Zoning Hearing Board's solicitor to confirm logistics. She tells him there will be no hearing, with little explanation given.

July 16, 2026State

DEP issues its determination on the stormwater objections, answering one of the residents' four. The other three are left unaddressed.

Public Records and Intellectual Property Notice

Source & Purpose: Documents hosted on this site are public records Stop PAX-1 obtained lawfully, through requests under Pennsylvania’s Right-to-Know Law and from the public filings, postings, and recorded plans of the agencies involved, and they are published strictly for public transparency, review, and informational purposes. External sources link to the original publisher; that material is neither hosted nor controlled by us.

Copyright & Intellectual Property: Stop PAX-1 claims no ownership of these documents. Each one remains the property of its author, who retains full copyright, trademark, and all other proprietary rights in it. The display of these documents under public disclosure laws does not grant any license or right to reproduce, redistribute, modify, or commercially exploit this material without the express written consent of the copyright holder.

No Endorsement or Professional Liability: These plans are provided “as-is” for historical and public reference only. They do not constitute engineering advice, and their inclusion does not imply an endorsement by Stop PAX-1 or by any firm or agency named. These plans may not be current, complete, or suitable for any construction, development, or professional application. Anyone using or relying on these documents does so entirely at their own risk.