Timeline

Updated August 18, 2026

See how we got here.

This was pushed through with real gaps. Here they are, in chronological order. Every date is on the public record, and most link directly to the source document.

25 milestones · 145 in the full record

2023

October 19, 2023Township

The Zoning Steering Committee's final draft of the new zoning ordinance is circulated. Section 2.01 lists five special overlay districts: Airport Hazard, Floodplain Conservation, Riparian Buffer, Redevelopment Opportunity and Wellhead Protection. The words "data center" appear nowhere in the 394-page draft.

2024

October 25, 2024Developer

At a Board workshop, the developer's attorney, PowerHouse CEO Doug Fleit, and the project team present the data center concept for the first time; the supervisors voice support the same day and send it to the Planning Commission. The minutes record no public comment.

December 4, 2024Developer

The developer's attorney emails Zoning Officer Mark Carpenter and the township zoning consultant a pre-drafted Data Center Overlay ordinance for the township's new zoning ordinance — sent outside any public meeting.

2025

January 7, 2025Township

The township zoning consultant confirms to the developer's attorney: "we have the Data Center Overlay language incorporated into the draft." The developer's text is now in the township's ordinance.

January 31, 2025Township

Zoning Officer Mark Carpenter emails the township's planning consultant to pass along direction from the Supervisors: "Allow Data Centers By Right in the Data Center Overlay District area (on the PennTerra & McNaughton properties along Country Club Road in the MU-1 Zoning District) and in the Industrial Districts." The same email conveys the Solicitor's opinion that the Comprehensive Plan is "obsolete and no longer relevant," so its Future Land Use Map "does not need to be updated before the Board of Supervisors consider the new Zoning Ordinance at a Public Hearing." That morning's workshop minutes record no mention of data centers, the overlay, or either property.

April 16, 2025Developer

The developer's attorney tells the township his client will file a standalone overlay amendment "for belts and suspenders." Later that evening, he retracts that intention: "Powerhouse has decided NOT to do a separate amendment."

April 17, 2025County

The County Planning Commission votes unanimously to deny approval of the township's full zoning rewrite "until CCPC comments are addressed." Zoning Officer Mark Carpenter attends and asks the county to approve it anyway, stating the comments can be addressed later through amendments.

April 23, 2025Developer

The developer's attorney files the standalone Data Center Overlay amendment (TPF 25-7) for the landowner, KMWW Partnership. The application says the zoning must be in place as soon as possible "or else the availability of power is jeopardized and with it, the viability of the data center project."

April 25, 2025Township

At a workshop, the developer's attorney urges speed — PPL power will be allocated on a "first-come, first available basis" — and the Board schedules the overlay hearing for May 30, with the developer paying for the advertising. The 35-day clock starts.

May 30, 2025Township

At a 7:30 a.m. public hearing with, in a supervisor's own later words, "very little public attendance," five people speak. Four ask the Board to wait for more information. None speaks in favor. The Board adopts Ordinance 3-2025 anyway, unanimously, 35 days after it took up the request.

July 15, 2025Federal

PAX-1 is announced as a ~$15 billion project at Senator McCormick's Energy and Innovation Summit; developer Igal Feibush joins a private roundtable with the President.

August 7, 2025State

DEP issues a Notice of Violation for the unpermitted line through the wetland on Country Club Road, citing the Clean Streams Law, and requests an after-the-fact permit application.

August 12, 2025Residents

Residents pack a township meeting with questions about the data center; PennLive reports the first organized resistance and skepticism.

August 18, 2025Developer

The Phase 1A land development plan — PPL's substation site — is submitted to the township.

September 3, 2025Township

The Board adopts Ordinance 7-2025, the comprehensive zoning rewrite: the overlay is folded in as Section 2.18, the land under it becomes MU-1 "Mixed-Use Neighborhood," and data centers become by-right in the Industrial district.

2026

January 5, 2026Township

The Board conditionally approves the preliminary subdivision: 693 acres, five lots, one data-center development.

January 23, 2026State

The State Historic Preservation Office rejects the developer's "no adverse effect" memo and formally finds the project WILL have an adverse effect on the Appalachian Trail.

April 13, 2026Developer

The developer's own noise study is completed: 532 generators across the campus.

May 6, 2026Township

In one meeting, the Board conditionally approves the final subdivision, the final Phase 1A plan, and the preliminary Phase 1B plan — 29 more waivers, modifications, and deferrals of township standards across the three approvals.

May 13, 2026Residents

Five couples who live beside the site file a substantive validity challenge with the Zoning Hearing Board, arguing the Data Center Overlay is illegal spot zoning. Pennsylvania courts have been striking down spot zoning where they find it since the 1960s; the challenge asks the Zoning Hearing Board to find it here.

June 3, 2026Residents

The residents appeal the May 6 approvals to the Cumberland County Court of Common Pleas, asking the court to review whether the township followed its own ordinances.

June 29, 2026Township

Nine days before the hearing, the residents' attorney Nathan Wolf calls the Zoning Hearing Board's solicitor to confirm logistics. She tells him there will be no hearing, with little explanation given.

July 16, 2026State

DEP issues its determination on the stormwater objections, answering one of the residents' four. The other three are left unaddressed.

August 6, 2026Residents

After the Zoning Hearing Board let its 60-day hearing deadline lapse, the residents file their spot zoning challenge in the Cumberland County Court of Common Pleas, asking the court to strike the Data Center Overlay.

August 13, 2026Residents

The two resident families appeal to the Environmental Hearing Board, challenging all four amendments that stretched a stormwater permit written for 58 homes across the 693-acre data center, and the DEP determination that answered only one of their four objections.

Public Records and Intellectual Property Notice

Source & Purpose: Documents hosted on this site are public records Stop PAX-1 obtained lawfully, through requests under Pennsylvania’s Right-to-Know Law and from the public filings, postings, and recorded plans of the agencies involved, and they are published strictly for public transparency, review, and informational purposes. External sources link to the original publisher; that material is neither hosted nor controlled by us.

Copyright & Intellectual Property: Stop PAX-1 claims no ownership of these documents. Each one remains the property of its author, who retains full copyright, trademark, and all other proprietary rights in it. The display of these documents under public disclosure laws does not grant any license or right to reproduce, redistribute, modify, or commercially exploit this material without the express written consent of the copyright holder.

No Endorsement or Professional Liability: These plans are provided “as-is” for historical and public reference only. They do not constitute engineering advice, and their inclusion does not imply an endorsement by Stop PAX-1 or by any firm or agency named. These plans may not be current, complete, or suitable for any construction, development, or professional application. Anyone using or relying on these documents does so entirely at their own risk.