Check our math

The numbers we worked out ourselves.

Most figures on this site come straight from a document, and we link the page they're on. The rest we worked out ourselves, from public data and the developer's own numbers.

9 times the electricity of all homes in Cumberland County#

The developer announced PAX-1 at 1.35 gigawatts. We worked out how much electricity that is in a year if the campus runs at 80 percent of it on average, about what power companies plan for. We set that beside a year of electricity for every home in Cumberland County: the Census's count of households, at the average Pennsylvania home's use.

Read the announcementGrid Strategies on data center use

If PAX-1 runs atA year's electricityThe county's homes
All of its 1.35 gigawatts11.8 billion kWh11.3 times
80 percent of it9.5 billion kWh9.1 times
Half of it5.9 billion kWh5.7 times

The math

106,427 households × 817 kWh a month × 12 months
= 1.04 billion kWh a year

The Census's household countEIA's home electricity use

1,350 megawatts × 80% × 8,760 hours in a year
= 9.46 billion kWh a year
9.46 billion kWh ÷ 1.04 billion kWh
= 9.1

About 9 times

The details

The developer's announcement of July 15, 2025 puts the campus at “1.35 GW of capacity with expandability up to 1.8 GW”: three campuses, each with “a dedicated 450 MW substation.” A gigawatt is a thousand megawatts. At 1.8 gigawatts and the same 80 percent, PAX-1 would use about 12 times the electricity of the county's homes.

No one has published how hard PAX-1 will run. Data centers run around the clock, so they use more of their capacity than most customers. Duke Energy plans for new large customers to average 80 percent of their peak, and Dominion Energy reported that its large data centers in Virginia averaged 82 percent of theirs in 2024. Some data centers draw less than they are built for: PG&E found its data centers' peaks averaged about two-thirds of their rated load, and in one utility's records fewer than half averaged more than 80 percent of their peak. Even at half its capacity, PAX-1 would use more than five times the electricity of every home in the county.

E3 on real data center loads

The Census counts 106,427 households in the county, give or take 704, in its American Community Survey for 2020 to 2024. The 817 kilowatt-hours a month is the average for a Pennsylvania home in 2024, from the U.S. Energy Information Administration. Homes in the county may use somewhat more or less than the state's average.

The figure is for the campus built out. The same announcement puts its first 300 megawatts in service by mid-2027.

1,333 homes within a mile of the site#

We took Cumberland County's 911 address points, its record of every address in the county, and kept the ones it marks as a home on a building. Then we measured each home's distance from the edge of the site.

See the county's address data

Measured from the nearest planned building instead, 1,760 homes sit within 2 miles, and 922 of them sit farther out than any home the developer's noise study modeled. How close and Impacts use those counts.

See where it modeled homesView the plan

Distance from the site's edgeHomes
1,000 feet260
A quarter mile454
One mile1,333
A mile and a quarter1,561
A mile and a half1,773
Two miles2,832

The math

1,142 of them in Middlesex ÷ 2,922 homes in the township
= 39%
191 of them in Silver Spring ÷ 1,333 within a mile
= 14%
The details

The county's records are as of September 28, 2026. Businesses are left out, and so are 92 addressed lots in new subdivisions where no home stands yet.

The farthest home the noise study modeled sits about 3,800 feet from a building. We placed the study's 16 homes from its map onto the developer's site plan and measured from there.

The four homes inside the site, on Country Club Road, are not counted. The nearest home outside it is about 80 feet from the line.

As a check, the 2020 Census counts about 1,030 to 1,060 housing units within the same mile. The county's records are newer, and they count addresses rather than the Census's housing units. On either count, more than 1,000 homes sit within a mile of the site.

See the Census blocks

About 16 homes on private wells within 1,000 feet#

No public record lists which homes are on public water. So we placed each home we counted on DEP's map of the areas public water systems serve. A home inside one is likely on public water. A home outside all of them likely has its own well.

See DEP's water service areas

Within 1,000 feetWithin a mile
Homes counted2601,333
Likely on public water2441,158
Likely on a private well16175
The details

DEP's map is as of September 29, 2026. Near the site, the public water comes from the Middlesex Township Municipal Authority. Most of the homes within 1,000 feet are in Country Manor West and The Meadows, which the authority's minutes say its 12-inch main serves. Eleven of the 16 likely on wells line Country Club Road, along the site's southern edge.

Read the authority's June 2026 minutes

The authority's June 2026 minutes say the developer finished moving its main on May 8, 2026. The drawing of the new main, in the authority's Right-to-Know records, shows it running along the site side of Country Club Road, past most of those eleven homes, so they may now be able to connect. We found no record of which, if any, have.

Two places needed a closer look, both more than 1,000 feet out. DEP's map splits two mobile home parks, and a park that size has to be on a regulated water system, not household wells, so we counted each park whole. Part of Cumberland Range Estates is missing from DEP's map, and the authority's minutes show that development's water lines being turned over to it in 2024, so we counted those 18 homes as public water.

Read the authority's November 2024 minutes

As a check, we looked at the state's records of wells that drillers have reported. Within a mile, 26 percent of the homes outside the service areas have a reported household well within 300 feet of them, against 4 percent of the homes inside. The county's own map of public water, which it calls generalized, puts 3 of the 16 homes within 1,000 feet inside a service area.

See the state's well recordsSee the county's water service map

These are estimates, neighborhood by neighborhood. DEP calls its boundaries approximate, and its map of the authority's area dates from February 2024. A home inside a service area may still use an old well, and a home outside may have a service line. A list of the authority's connections, or a knock on each door, would settle it.

615 acres of prime or statewide farmland#

USDA's soil survey maps the soils of every county and rates each one for farming. We took every soil area that touches the site, cut each one to the site's outline, and added up the acres by rating.

Open USDA's Web Soil Survey

USDA's ratingAcresShare
Farmland of statewide importance572.883%
Farmland of local importance44.26%
Prime farmland41.76%
Not prime farmland34.25%

The math

572.8 acres of statewide importance + 41.7 acres of prime
= 614.5 acres
614.5 acres ÷ 692.9 acres in the site
= 89%

615 acres, about 9 in 10

The details

We pulled the soil areas from USDA's Soil Data Access service on September 29, 2026. Cumberland County's survey is the version of September 5, 2025. Most of the 34 acres rated not prime are steep slopes.

Federal rules define prime farmland as land “that has the best combination of physical and chemical characteristics for producing food, feed, forage, fiber, and oilseed crops.” Each state sets its own criteria for farmland of statewide importance.

What the classes mean

The survey maps soils at county scale, so the acres are close, not survey-exact. The ratings describe the soil, not how the land was used, though aerial photos from before construction show it in crops. To check the ratings yourself, open USDA's Web Soil Survey, draw the site as your area of interest, and look up its farmland classification.

PAX-1 will nearly double Middlesex's industrial land.#

Cumberland County's planning department recorded the land use of every parcel in the county in 2020. We added up the Middlesex land it lists as industrial, measured from the parcel shapes, added two warehouses the survey misses, and set the PAX-1 site beside it.

See the county's land use data

The survey lists the 62-acre warehouse at 100 Carolina Way as agricultural, though the county's own record for the parcel codes it a warehouse, with a $33.1 million building that shows in the county's aerial photos from 2018 on. The 34-acre warehouse at 1700 Harrisburg Pike was still under construction in the county's 2020 aerial photos, and the survey lists its land as vacant. It was finished by 2021.

See the county's recordSee the warehouse in 2018See the Harrisburg Pike warehouse in 2021

AcresShare of the township
Industrial land in the 2020 survey6894.2%
The two warehouses the survey misses950.6%
Industrial land before PAX-17844.8%
The PAX-1 site6934.2%
Both together1,4779.0%

The math

689 acres in the 2020 survey + 95 acres in the two warehouses
= 784 acres
784 acres + 693 acres of PAX-1
= 1,477 acres
1,477 acres ÷ 784 acres
= 1.9

PAX-1 alone will nearly double it

The details

We took all 2,459 Middlesex parcels in the survey, as published on September 28, 2026, and checked them again on October 6. The township covers 16,412 acres. In the survey, thePAX-1 parcels were 546 acres of farmland and 147 acres the county classed as public.

See the township boundary

The county codes each parcel's use for its tax records, and the survey sorts those codes into its categories. Its industrial land is truck terminals, warehouses and manufacturing. The record for 100 Carolina Way carries code 398, which the county's code list names Warehouse, yet the survey sorts the parcel as agriculture. The warehouse at 1700 Harrisburg Pike replaced a motel, and the survey records its land as vacant commercial land.

See what code 398 means

We don't count the natural gas plant UGI opened on 46 acres of Claremont Road farmland in 2025. The county's plan review calls it industrial, but its land-use surveys file utility land as public. Counting it, PAX-1 would add 84 percent. We checked the county's plan reviews, tax records and aerial photos for anything else built since 2020 and found no other industrial land in use as of the county's 2024 photos. A trailer lot SAIA had approved in 2024 wasn't built yet.

The county files PAX-1's own plans as industrial land use, and the Township's 2025 zoning allows data centers by right in its industrial district.

On the Township's 2025 zoning map, 724 of the 784 acres sit in its Industrial and Light Industrial-Commercial districts. None of the PAX-1 site does. All of it is zoned MU-1, Mixed-Use Neighborhood, and its edge borders neighborhood and farm zoning all the way around.

View the zoning map

19 times the permit's area#

The stormwater permit PAX-1 builds under was issued for Cumberland Knoll, a 58-home subdivision. From 2018 until its third amendment in December 2025, the permit covered 36.37 acres. Since then it has covered 693.44 acres.

View the appeal

The math

693.44 acres now ÷ 36.37 acres before
= 19.1

19 times the area

The details

The permit's description calls Cumberland Knoll “58 total units on 15.3 acres.” That is the subdivision's lot area. The permit's own area was the 36.37 acres its notices of intent state, so we compare the permit's area then to its area now.

More than 1.5 million gallons from an inch of rain#

The developer's engineer told the Supervisors each of the 16 buildings is about 156,000 square feet. USGS says an inch of rain on an acre is 27,154 gallons.

USGS: an inch of rain on an acreWatch the 156,000 square feet

The math

16 buildings × 156,000 sq ft
= 2,496,000 sq ft of roof
2,496,000 sq ft ÷ 43,560 sq ft in an acre
= 57.3 acres
57.3 acres × 27,154 gallons
= 1,556,000 gallons

More than 1.5 million gallons

The details

That counts the roofs alone. Roads, parking and equipment yards add more. At the August 19, 2026 meeting, the developer gave larger footprints: about 123,000 square feet for the first two buildings and 194,000 for the rest. That comes to about 68 acres of roof and 1.8 million gallons an inch. We use the smaller figure.

146 million gallons of water allocated a year, 2,367 homes' worth#

The municipality has allocated the campus 400,000 gallons of water a day. Over a year, that comes to 146 million gallons. PennLive reported the daily amount as one “engineers say is equal to the consumption from 2,367 dwelling units,” the daily water of that many homes.

View the meeting notesPennLive on the water

The math

400,000 gallons a day × 365 days
= 146 million gallons a year
400,000 gallons a day ÷ 2,367 homes
= 169 gallons a home
The details

The 146 million gallons is the allocation, the most the campus may draw. In June 2026, the general counsel of one of the companies behind PAX-1 told the Planning Commission that its hydrologist and tenants expected “probably somewhere around twenty-two million gallons” a year. We have found no document that states that figure.

Watch the developer's estimate

The 2,367 is not our count. On the Impacts page we set it beside the 1,333 homes we counted within a mile of the site.

693 acres, almost six Hersheyparks#

The site is the four PAX-1 parcels in Cumberland County's tax map. Measured from their shapes, they cover 692.9 acres. The subdivision plan and the stormwater permit give 693, the figure we use everywhere on this site. The county planning department puts the Data Center Overlay, which covers the same four parcels, at about 694 acres. Every count on this page measures from this outline.

View the minutesView the county review

The math

693 acres ÷ 121 acres of Hersheypark
= 5.7

See Hersheypark's page

Almost six Hersheyparks

The details

The four parcels are numbers 21-06-0015-001, -013, -014 and -015.

10 more data centers within 60 miles#

We counted every data center project within 60 miles of the site that was on DEP's data center permit tracker or before a local government on September 29, 2026. Of those 12, 2 stopped after residents pushed back, and the rest are proposed or under review.

See the tracker

ProjectMilesStatus
Monroe Township, Cumberland County8.6In the works
Highlands East, Swatara Township, Dauphin County17.3In the works
Highlands West, Swatara Township, Dauphin County17.3In the works
South Hanover Township, Dauphin County21.8Stopped
Londonderry Township, Dauphin County23.8In the works
South Annville Township, Lebanon County32.0Stopped
Granville Township, Mifflin County34.0In the works
Lancaster AI Hub West, City of Lancaster43.8In the works
Lancaster AI Hub East, City of Lancaster47.7In the works
Mount Carmel Township, Northumberland County52.0In the works
Butler Township, Schuylkill County54.1In the works
New Castle Township, Schuylkill County58.6In the works

The math

12 projects − 2 paused or withdrawn
= 10
The details

Miles are straight-line distances from DEP's point for PAX-1. Each project sits at DEP's own point where it has one, otherwise at its street address, or at the middle of its township where no address has been published: South Hanover, South Annville and Granville.

We left off projects with only reported interest and no filing: several townships in York County, the Dauphin Highlands golf course sale, and the York 2 Energy Center announcement, along with one golf course taken out of consideration before any filing.

  • Monroe Township, Cumberland County: The partnership behind PAX-1 asked in April 2026 to present plans for a data center.

    The letter to Monroe

  • Swatara Township, Dauphin County: Highlands East, a $10.5 billion campus on 157 acres, with plans before the township. DEP lists it as proposed.

    WITF on SwataraSee the tracker

  • Swatara Township, Dauphin County: Highlands West, by the same company. DEP lists it as proposed.

    See the tracker

  • South Hanover Township, Dauphin County: Two data centers at a former quarry, filed in June 2026 and put on hold in August after residents raised concerns.

    Read about the filingRead about the pause

  • Londonderry Township, Dauphin County: DEP lists it as proposed.

    See the tracker

  • South Annville Township, Lebanon County: A $1.7 billion campus, withdrawn in May 2026 after the planning commission voted unanimously against the rezoning it needed.

    LebTown on South Annville

  • Granville Township, Mifflin County: One of the companies behind PAX-1 applied in July 2026 for six buildings, two days before a planned pause on data centers there.

    abc27 on Granville

  • City of Lancaster: Lancaster AI Hub West, at 1375 Harrisburg Pike, under a benefits agreement with the city.

    See the city's page

  • City of Lancaster: Lancaster AI Hub East, at 216 Greenfield Road. DEP has finished its review.

    See the city's pageSee the tracker

  • Mount Carmel Township, Northumberland County: DEP lists it as proposed.

    See the tracker

  • Butler Township, Schuylkill County: A campus for the company Nebius, under DEP review.

    See the tracker

  • New Castle Township, Schuylkill County: DEP lists it as proposed.

    See the tracker

How tall and how wide the buildings would look from your home#

For height, we compared the buildings with a two-story house, about 25 feet tall. A building three times as tall looks as tall as the house when it's three times as far away. So a 75-foot building, the overlay's height limit, looks from your home as tall as a house a third as far away.

The overlay today

For width, we used the rule of thumb that a fist held at arm's length covers about 10 degrees of what you see, and worked out the angle 1,000 feet of building fills from your distance to the nearest one.

The math

75 feet ÷ 25 feet
= 3, so a house a third as far away looks as tall
2 × arctan(500 feet ÷ your distance)
= the angle 1,000 feet of building fills
At 1,400 feet: 2 × arctan(500 ÷ 1,400)
= 39 degrees, about four fists
The details

We used the height limit, not the plans, because heights differ across the three campuses and rooftop equipment the limit doesn't count can stand higher. The math leaves out the land between you and the site. Hills, trees and other buildings decide whether you see them at all.

The smaller sums#

35 days

April 25, 2025 to May 30, 2025 is the last 5 days of April and 30 days of May.

View the minutesView the ordinance

$44 million for the land

$30 million for three parcels + $14 million for the fourth, in two deeds.

View the $30 million deedView the $14 million deed

Walls nearly twice the height limit

Walls about 72 feet ÷ the 40-foot limit = 1.8.

View the ordinanceWatch the 72 feet

About 2× taller

The overlay's 75-foot limit ÷ the neighborhood's 40-foot limit = 1.9.

View the ordinance

109× larger lots

25 acres is 1,089,000 sq ft. 1,089,000 ÷ the neighborhood's 10,000 sq ft = 108.9.

View the ordinance

1.4× more paved

The overlay's 70% ÷ the neighborhood's 50% = 1.4.

View the ordinance

More than 1,400 megawatts of generators

566 generators × 2.5 megawatts = 1,415 megawatts, plus 16 house generators × 0.6 megawatts = 9.6. That's 1,424.6 megawatts in all.

View the equipment table

More than 40% of the spare water

400,000 gallons a day ÷ the water system's spare capacity, about 910,000 gallons a day = 44%.

View the allocationView the capacity figures

PAX-1 could hold 8 sites like Great Oak

PAX-1's 693 acres ÷ the 83 acres of Amazon's Great Oak campus = 8.3, rounded down to 8. Each account's card on Near Other Data Centers and How Close Are You to PAX-1? divides PAX-1's acreage by that site's the same way.

View the four parcelsThe county's parcel record

Found a mistake in our math? , and we'll fix it and say so on our corrections page.