16 hyperscale data centersdo not belong on farmlandsurrounded by homes
In one decision, the Board of Supervisors nearly doubled the industrial land in Middlesex Township. They changed this community forever, without weighing the impact on residents, livestock, wildlife or visitors.
Sign no matter where you live to get updates on the fight.
Middlesex Township · Cumberland County · Pennsylvania
The bare ground past the trees is the PAX-1 site, 2026
Where the fight stands#
Updated October 5, 2026
Next in court
November 13, 2026
The county court hears evidence on the merits of the spot zoning case, on our request to halt construction.
Construction continues. On September 22 the court declined to pause the work for now. On October 5 it found that the mandatory hold in state law doesn't apply to the spot zoning case.
View the September 22 orderView the October 5 orderView our request to enforce the hold
- The spot zoning challengeIn county court. Asks the court to strike down the special zoning written for this site.Next: The November 13 hearing on the merits.
- The land use appealsIn county court. Each asks the court to overturn the Supervisors' approvals of the plans.Next: Our brief is due November 2. Argument is January 12, 2027.
- The stormwater permit appealBefore a state board. Asks the Environmental Hearing Board to pull the permit for the first phases.Next: Evidence gathering runs until February 10, 2027.
- In county courtThe spot zoning challengeAsks the court to strike down the special zoning written for this site.Next: The November 13 hearing on the merits.
- In county courtThe land use appealsEach asks the court to overturn the Supervisors' approvals of the plans.Next: Our brief is due November 2. Argument is January 12, 2027.
- Before a state boardThe stormwater permit appealAsks the Environmental Hearing Board to pull the permit for the first phases.Next: Evidence gathering runs until February 10, 2027.
What is PAX-1?#
A $15 billion campus of 16 data centers: warehouse-sized buildings full of computer servers that run day and night, on farmland in Middlesex Township.
A partnership of Pennsylvania Data Center Partners and PowerHouse Data Centers is building it beside the Conodoguinet Creek, a third of a mile from the Appalachian Trail. 1,333 homes stand within a mile of it.
Construction has started. So have three legal challenges.

Buildings, drives and generator yards drawn from the developer's own plans, the substations and the gravel laydown yard from the fences on its site plans, homes from the county's address records. Aerial imagery: USGS and USDA, taken before construction.
The developer's planThe generator yardsThe substationsThe laydown yardCheck our math on the homes
How close are you?
See how far your home is from PAX-1.#
Enter an address to see how far it sits from the site and what to expect there if PAX-1 is built.
We find addresses with the U.S. Census Bureau's address search and Cumberland County's address map. We don't save addresses or locations. We only count lookups by rough distance from the site and by area, such as Middlesex Township.
How big is it?
694 acres#
Almost six Hersheyparks.
Hersheypark lists itself at 121 acresCheck our math on the site's size
“one of the largest projects in the whole Harrisburg area in the last 50 years”
1.9×
PAX-1 alone will nearly double the industrial land in Middlesex Township.
- Industrial land in Middlesex784 acres
- With PAX-11,478 acres
Most of its sixteen buildings are about 900 feet long and 200 feet wide. Their walls rise about 72 feet, nearly twice the 40-foot limit in the zoning under and around the site. Rooftop penthouses reach about 83.
“The building is two stories.”
What does it mean for me?
It doesn't stop at the property line.#
Power and our bills
9×
the electricity of all homes in Cumberland County
Our grid's independent monitor found data centers added $29.4 billion to the region's capacity costs, the price of keeping enough power plants ready, for June 2025 through May 2029, and PPL says rising capacity prices added about $20 a month to its average home's bill. PAX-1 plans for 1.35 gigawatts more.
Check our math on the electricityRead the reportSee PPL's page
Water
146 million
gallons of water allocated a year
The Township's water authority set it aside for the campus, 400,000 gallons a day. Engineers say it equals what 2,367 homes use.
- The water PAX-1 is allocated2,367 homes' worth
- Every home within a mile of it1,333 homes
Generators and air
582
diesel generators
The Clean Air Board told the Supervisors that Cumberland County's air already gets an F from the American Lung Association for short-term particle pollution. The developer's engineer calls testing the generators “a daily activity.”
See the county's gradesView the equipment tableWatch the Clean Air BoardWatch “a daily activity”
Noise
24/7
mechanical noise
Middlesex allows data centers 70 decibels at the property line. To protect sleep, the World Health Organization advises no more than 45 outside homes at night.
The Appalachian Trail
1/3 mile
from the Appalachian Trail
The state found PAX-1 will have an adverse effect on the Trail. The Trail Conservancy counts upwards of 150,000 visitors to this part of the Trail each year.
Why it doesn't belong here
People who live beside other data centers describe the hum, the lights and the blasting, from next door to a mile away.
See all eight costsWhat it's like to live next to oneWhat our neighbors say
How did it get approved?
The developer was allowed to write their own rules.#
~80%
of the data center overlay in today's zoning law matches the developer's draft, word for word
35 days
from the developer's request to law, adopted at 7:30 on a Friday morning
19×
the area the stormwater permit first covered, from 36 acres for 58 homes to 693 acres now
In Middlesex, a warehouse needs a public hearing. A hyperscale data center does not.
“We changed the ordinance. Unfortunately, there's really nothing the board of supervisors can do to stop this project.”

Can it still be stopped?
They haven't won yet.#
Yes, bulldozers are rolling, but that doesn't make it legal, and it doesn't make it final. We see significant issues with how this was approved, and we are challenging them in every way we can.
Zoning drawn for the developer's land, and nowhere else.
We're challenging the zoning.
An environmental study written by the developer's own engineer.
We've appealed the plan approvals.
A stormwater permit amended four times without public comment.
We've appealed the permit.
The PAX-1 site, September 22, 2026
Why does it matter beyond Middlesex?
If it can happen here, it can happen next to you.#
The companies behind PAX-1 are already looking at other townships.
Monroe Township, Cumberland County
144 acres
secured by the partnership behind PAX-1, which asked in April 2026 to present plans for another data center there
Granville Township, Mifflin County
6 buildings
filed for in July 2026 by one of the companies behind PAX-1, two days before a planned pause on data centers there
10 other data centers, Monroe and Granville among them, are in the works within 60 miles of Middlesex.
- PAX-1
- Proposed or under review
- Paused or withdrawn after residents pushed back
Each township still writes its own rules. Statewide, the Governor wrote in August 2026 that most proposed data centers are “speculative in nature, with no identified end user.”
DEP's trackerThe Governor's orderCheck our math on the nearby data centers
All 12 projects
Monroe Township, Cumberland County: The partnership behind PAX-1 asked in April 2026 to present plans for a data center.
Swatara Township, Dauphin County: Highlands East, a $10.5 billion campus on 157 acres, with plans before the township. DEP lists it as proposed.
Swatara Township, Dauphin County: Highlands West, by the same company. DEP lists it as proposed.
South Hanover Township, Dauphin County: Two data centers at a former quarry, filed in June 2026 and put on hold in August after residents raised concerns.
Londonderry Township, Dauphin County: DEP lists it as proposed.
South Annville Township, Lebanon County: A $1.7 billion campus, withdrawn in May 2026 after the planning commission voted unanimously against the rezoning it needed.
Granville Township, Mifflin County: One of the companies behind PAX-1 applied in July 2026 for six buildings, two days before a planned pause on data centers there.
City of Lancaster: Lancaster AI Hub West, at 1375 Harrisburg Pike, under a benefits agreement with the city.
City of Lancaster: Lancaster AI Hub East, at 216 Greenfield Road. DEP has finished its review.
Mount Carmel Township, Northumberland County: DEP lists it as proposed.
Butler Township, Schuylkill County: A campus for the company Nebius, under DEP review.
New Castle Township, Schuylkill County: DEP lists it as proposed.
Middlesex Township is the line in the sand.Stop them here, and we set the precedent that communities are shaped by the people who call them home, not by outside developers.

Who are we?
We're your neighbors.#
We didn't ask for this fight, but everyone who should have protected us failed, so we chose to stand in the gap. We're not activists or experts, we're ordinary people like you.
What can I do?
Help us Stop PAX-1#
Updated live
2,768
neighbors have added their names
Join the fight
Wherever you live, we're all neighbors in this. Stand with us against PAX-1 and get every update as the fight moves forward.
$52,322
raised toward our $100,000 legal fund
Lawyers stop bulldozers.
Laws only hold when someone enforces them. That falls to us now, and every dollar buys the attorneys and experts we need to push back.
Want to go deeper?
The whole story, with the record behind it.#
Start here
Why it doesn't belong here
How it got approved
How we stop it
The record
- TimelineEvery step, from the first zoning draft to the latest ruling
- Township MeetingsVideo, transcript, and summary of past meetings
- DocumentsThe plans, permits, reviews, and ordinances
- In the NewsWhat reporters have covered, and the press kit
- Check Our MathThe math behind the numbers we worked out ourselves