Judge sets November 13 hearing on the Middlesex families' spot zoning challenge

Where you live

How close are you to PAX-1?

See how far your home is from PAX-1, the 16-building data center campus near Carlisle, and what to expect there.

We look up addresses with the U.S. Census Bureau and with Cumberland County's address points, hosted by Penn State. We don't save addresses or locations. We only count lookups by rough distance from the site and by area, such as Middlesex Township.

An aerial photo of the PAX-1 site, outlined in orange, with a dot on every home around it

The noise study

The developer only modeled noise at homes up to 3,800 feet from its buildings.#

922 of the 1,760 homes within 2 miles of those buildings sit farther out.

See where it modeled homesCheck our math on the homes

Look up your home

What to expect

What PAX-1 will most likely mean for the homes around it, from the developer's plans, Virginia's legislative auditors and people who live near other data centers.

  1. A constant low hum

    Virginia's auditors describe it as a constant drone, like a home air conditioner at industrial scale, and some residents there report lost sleep. Middlesex's limit, 70 dBA at the property line, uses a scale that doesn't fully count a hum like this, and it doesn't apply during a power outage.

    Virginia on the constant humVirginia on noise limitsView the noise limit

    How much noise pollution, in dBCHomes near the site, beside places with and without a data center

    Homes near the site

    The developer's April model, at 14 of the 16 homes it modeled

    58 to 64 dBC

    Compared with

    • Homes near Amazon's data centersAbout the same

      Measured at night, with some traffic, in Prince William County, Virginia

      60 to 63 dBC
    • Near other data centers thereMore noise

      Measured at night

      66 to 73 dBC
    • A quiet nightLess noise

      No data center, in rural Nokesville, Virginia

      48 dBC

    dBC. Bars start at 40.

    dBC counts the hum fully; dBA, the scale noise limits use, turns it down. In a power outage, the developer's study gives these homes 63 to 70. It gives the other two 48 and 42, without saying why. The developer's study says many agencies and practitioners use 65 to 70 dBC to avoid low-frequency problems, without naming any. View the study on dBC

    The developer's levels, home by homeWhere the measurements come from

    Great Oak, Virginia

    “It's beyond frustrating that I can't protect my children.”

    Carlos Yanes, 2025

    About 600 feet from Amazon's data centers.

    Residents called the police over the noise in 2022. In 2025, after Amazon's fixes, the Prince William Times found the neighborhood still “plagued by a low-frequency roar.”

    Amazon: 83 acres, four data centers

    PAX-1 could hold 8 sites this size

    Prince William Times on Great Oak in 2025Prince William Times on Amazon's 2023 fixThe county's parcel record

  2. Six years of construction

    Virginia's auditors found that building a campus this size means years of loud work and heavy truck traffic. PAX-1 is scheduled to take until spring 2032, and the Township says work is allowed Monday through Saturday, generally from 6 a.m. to 7 p.m. Blasting is part of the work, and inspecting homes beforehand isn't legally required, though the Township's minutes say contractors are offering it.

    Virginia on constructionRead it in the June 3 minutesRead it in the April 24 minutes

    The developer's construction schedule
    Today
    • Site work for all threeMarch to November 2026

    • Campus 1June 2026 to December 2028

    • Campus 2March 2028 to May 2030

    • Campus 3August 2029 to spring 2032

    2026202720282029203020312032

    View the site work and Campus 1View Campus 2 and 3Watch how the campuses are numbered

    Point Pleasant, West Virginia

    “Our house just shakes and vibrates all day. You can hear toilet seat just rattling on the toilet. You'll see the trash can go across the floor.”

    Joshua Jeffers, May 2026

    Beside Nscale's construction, in the neighborhood he has lived in for 20 years.

    The same story reports that a month's worth of rain in one weekend overwhelmed the site's erosion controls and flooded homes.

    Nscale: 2,200 acres

    About 3 times the size of PAX-1

    WCHS on the shaking housesWatch WCHS's reportWCHS on Point Pleasant

  1. Buildings and lights in view

    The zoning lets the buildings stand up to 75 feet tall, about three times a two-story house. Many data center sites run bright security lighting, and PAX-1's plans keep its lights at the same levels after hours, though the developer's engineer told the Supervisors most would be off or dimmed.

    Virginia on site lightingView the plans' lighting noteWatch “dimmed to that lower standard”Check our math on how the buildings would look

    Abilene, Texas

    “You don't need to turn the lights on to walk around the house at night because there's so many lights.”

    Rusty Towell, September 2026

    200 feet from the data center, which has grown to his property line.

    He bought land zoned for homes before the land to his north was rezoned. The campus has its own gas power plant.

    OpenAI's Stargate: 777.6 acres, eight buildings

    About the size of PAX-1

    KXAN on AbileneTaylor County's appraisal recordCrusoe's announcement

  2. Diesel generators

    The developer's noise studies list at least 582 diesel generators, more than ten times the average Virginia site's 54, and its engineer said testing them would be “a daily activity.”

    View the equipment tableVirginia's average siteWatch “a daily activity”

    Aurora, Illinois

    “Cyrus had to run their generators three days in a row, 24 hours. It was nonstop noise.”

    Laura Evans, March 2026

    About a thousand feet from CyrusOne's campus to the backyard.

    CyrusOne's own notices confirm a transformer failure in April 2025 and about a dozen announced generator runs since, besides the monthly tests.

    CyrusOne: 16 acres, three data centers

    PAX-1 could hold 43 sites this size

    FOX 32 on AuroraCyrusOne's generator noticesWatch ABC News's reportCyrusOne on its Aurora campus

  3. Water

    Many homes near the site are on the Township authority's public water. PAX-1 is allocated 400,000 gallons a day from it. Its customers in Middlesex use 560,000 on an average day, not counting what it sends on to North Middleton Township, and the authority's memo says a new well “or other sources of supply will be necessary.”

    View the allocationThe authority's current useView the authority's memo

  4. Your electric bill

    The regional grid's independent monitor found that existing and forecast data centers added $29.4 billion to its capacity costs, the price of keeping enough power plants ready, from June 2025 through May 2029, and PPL says higher capacity prices have added about $20 a month to its average home's bill.

    Read the reportSee PPL's page

    Aurora, Illinois

    “Our electric bills this past year are probably 50% higher than they've been years past.”

    Bryan Castro, February 2026

    Behind CyrusOne's campus.

    Nothing in the story ties his bill to the campus, and CyrusOne says it pays for all the electricity it uses, at rates set under Illinois' rules.

    CyrusOne: 16 acres, three data centers

    PAX-1 could hold 43 sites this size

    ABC7 on AuroraCyrusOne on its Aurora campus

People living beside data centers across the country, most of them smaller than PAX-1, describe what it's like.

Read what they say

What the developer's studies leave out

  • The equipment it will install. The Township's own consultant asked for the makes and models, to check the noise model. The developer said it couldn't disclose them without disclosing the end user.

    Watch the consultant's report

  • Its louder June plans. The June update lists more and louder equipment, raises each large generator from 65 to 75 dBA, and gives no level at any home.

    View its June equipment tableView the June generator levelView its June results

  • The air. We found no air model for PAX-1's generators in the public record. The developer has agreed to give the Township copies of its state air permit filings once it makes them.

    The air terms

What you can do

Add your name#

Then send this page to a neighbor.

The next public meeting is the Board of Supervisors, Workshop Meeting, Friday, October 30 at 7:30 a.m. See the calendar

Where residents won

Speaking up has worked elsewhere.#

In Pennsylvania

  • Hampden Township, Cumberland County

    Dozens of residents spoke for more than two hours against letting data centers into an office park beside their homes, and in September 2025 the commissioners unanimously turned it down. Their July 2026 rules allow data centers only in the industrial district, after a public hearing.

    abc27 on the hearingRead the September voteRead the rules they adopted

  • Montour County

    More than 3,000 signatures on petitions opposed rezoning about 870 acres of farmland for Talen Energy. In February 2026 the commissioners voted 3-0 to deny it, and the county's rules now keep data centers 1,000 feet from the property lines of homes, schools and parks.

    Inside Climate News on MontourRead the voteRead the ordinance

  • Hazle Township, Luzerne County

    A crowd of about 100 turned out, and in November 2025 the supervisors voted unanimously to deny a 15-building data center campus. A county judge denied the developer's appeal, and the township declared a 180-day pause while it writes data center rules. Doreen Cherenyock, across from the site, had videos of the early work “going on 24 hours a day, cutting, blasting.”

    FOX56 on the voteTimes Leader on the ruling and the pauseFOX56 on the pauseWVIA on the site work

  • Salem Township, Luzerne County

    After residents complained about a bitcoin mine's fans through the night, the township adopted a noise ordinance in June 2024. It covers data centers, limits sound at homes to 50 decibels overnight, and allows generator tests only from 10 a.m. to 6 p.m.

    FOX56 on the complaintsRead the ordinance

In other states

  • Port Washington, Wisconsin

    Residents pushed the city to stop round-the-clock construction at a data center site. Its plan commission set an end date, limited deliveries to 6 a.m. to 8 p.m., and required the site's lights to drop to security levels after 8:30 p.m.

    Ozaukee Press on the limits

  • Lowell, Massachusetts

    A judge granted residents' request to pause four new diesel generators at a data center while their lawsuit over its air permits goes forward.

    GBH on the pause

  • Henry County, Virginia

    After 37 residents spoke against data centers at a July hearing, the supervisors sent the rules back. In August they adopted stricter ones, including generator tests only on weekdays from 9 to 5 and a noise test every year.

    Read the July hearingRead the rules they adopted

What the county and other places require

Fund the fight

Lawyers stop bulldozers.

The fight over PAX-1 happens in court, and it runs on briefs, expert witnesses, and filing fees.

Fund the Fight100% goes to the legal fund.