The developer is claiming transparency with a timeline of their own, but they got a few things wrong, so we’ve fixed it for them 👍

The developer's attorney sent the township a fully drafted data center overlay. The township incorporated it into the draft zoning ordinance.
At their meeting, the supervisors directed that data centers be allowed by right on the developer's site and in the industrial districts. We know from an email. The meeting minutes don't mention it.
“For belts and suspenders, we are going to submit a request for an amendment to the current zoning ordinance.”
The commission was told the supervisors were in favor, and that the developer needed it in place to reserve power.
The county recommended waiting for the new ordinance and updating the comprehensive plan.
The township didn't wait.
PAX-1 files its first land development plans under the new overlay.
The developer holds its first public meeting for residents at the Carlisle Sports Emporium.
Their page gives you nothing to check. No documents, no links, no sources. Every entry on ours links to its source.
Even if you're not against 16 hyperscale data centers on farmland surrounded by homes, this sequence of events should alarm you.
Please consider funding our fight. Learn more about it and donate at